Sizing a trapezoidal roadside channel: Manning's normal depth, critical depth, and Froude number
A roadside ditch along a new commercial driveway has to carry the 10-year flow without overtopping or scouring out. This solves it the way a reviewer can check by hand: Manning's equation for normal depth (iterated), the resulting velocity, the critical depth and Froude number to fix the flow regime, and a permissible-velocity check on the grass lining. No proprietary charts — every number reproduces from the equations.
Channel inputs
The geometry and hydraulics an engineer actually fills out:
| Parameter | Value | Source |
|---|---|---|
| Design discharge, Q | 25 cfs | 10-yr peak from watershed analysis |
| Bottom width, b | 2.0 ft | Channel cross-section |
| Side slope, z (H:V) | 3:1 | Mowable, stable side slope |
| Longitudinal slope, S0 | 0.010 ft/ft (1.0%) | Profile grade |
| Manning's n | 0.030 | Established grass lining, good condition |
Step 1 — Manning's equation and channel geometry
Manning's equation in US customary units:
For a trapezoid with bottom width b and side slope z (horizontal:vertical), at depth y:
Collecting the constants, (1.49/n)·S₀^½ = (1.49/0.030)(0.010)^½ = 49.67 × 0.1 = 4.967, so normal depth is the y that satisfies:
Step 2 — Normal depth by iteration
There's no closed form for y in a trapezoid, so iterate on A·R^(2/3) until it hits 5.033:
| Trial y (ft) | A (ft²) | P (ft) | R (ft) | A·R2/3 |
|---|---|---|---|---|
| 1.15 | 6.268 | 9.273 | 0.676 | 4.83 |
| 1.20 | 6.720 | 9.590 | 0.701 | 5.30 |
| 1.17 | 6.447 | 9.400 | 0.686 | 5.01 |
At y = 1.17 ft, A·R2/3 = 5.01 ≈ 5.033. Normal depth yn = 1.17 ft.
Step 3 — Velocity and capacity
With A = 6.447 ft² at normal depth:
Top width and the freeboard you'd carry to the channel lip:
NCDOT roadside channels typically carry 0.5 ft of freeboard, so build the section to ~1.67 ft total depth (≈ a 2-ft-deep ditch).
Step 4 — Critical depth and flow regime
Flow is critical when the Froude number equals 1, i.e., when Q²·T = g·A³. Solve for the critical depth yc:
Iterating the trapezoid geometry, yc ≈ 1.05 ft gives A = 5.41 ft², T = 8.30 ft, A³/T = 19.1 ≈ 19.41. Critical depth yc = 1.05 ft.
Froude number at normal depth, with hydraulic depth D = A/T = 6.447/9.02 = 0.715 ft:
Fr = 0.81 < 1, and yn (1.17) > yc (1.05): the flow is subcritical — both checks agree, as they must. Subcritical flow is controlled from downstream, so the tailwater at the outlet sets the profile.
Step 5 — Lining and erosion check
The computed 3.9 ft/s has to be below the permissible velocity for the lining:
| Lining | Permissible velocity | Verdict at 3.9 ft/s |
|---|---|---|
| Bare earth (silt loam) | ~2.5 – 3.5 ft/s | Exceeded — will scour |
| Established grass, good cover | ~4 – 5 ft/s | OK |
| Turf reinforcement mat / riprap | > 6 ft/s | OK with margin |
The design is fine once the grass is established, but bare at construction startup it would erode. Specify a temporary liner (erosion-control blanket) until vegetation takes, or flatten the grade. Dropping S0 to 0.5% drops the velocity to ~3.1 ft/s and raises normal depth — see the table below.
What changes if you tweak the inputs
| If you change… | The result moves… |
|---|---|
| Slope 1.0% → 0.5% | yn rises to ~1.34 ft; V drops to ~3.1 ft/s (gentler, deeper, slower) |
| n 0.030 → 0.040 (heavier grass) | yn rises to ~1.32 ft; V drops to ~3.2 ft/s |
| Bottom width 2 ft → 4 ft | yn drops to ~0.95 ft; wider, shallower section |
| Q 25 → 40 cfs | yn rises to ~1.49 ft; V to ~4.3 ft/s — re-check the lining |
| Side slope 3:1 → 2:1 | Slightly deeper normal depth, narrower top width |
Open this channel in HydroComplete
The Conveyance engine solves Manning's normal depth, critical depth, and Froude number for 14 channel/closed-conduit shapes. Change the slope, the lining n, or the geometry and watch depth, velocity, and regime update instantly.
Sources and further reading
- Chow, V. T. (1959). Open-Channel Hydraulics. McGraw-Hill — Manning's equation, normal and critical depth.
- USDA-NRCS. National Engineering Handbook, Part 654 — Stream Restoration Design. Manning's n values.
- FHWA. Hydraulic Design of Highway Culverts (HDS-5). Open-channel approach and tailwater.
- NCDOT. Guidelines for Drainage Studies and Hydraulic Design. Roadside channel and permissible-velocity criteria.
— Michael Flynn, PE
This worked example uses HydroComplete's Conveyance engine for the Manning, normal-depth, and critical-depth solvers. Open the scenario in the app to verify or modify any input.
Related worked examples
- Sediment basin sizing for a 5-acre residential subdivision in Mecklenburg County, NCFull RUSLE → Camp's → 7-bin Stokes/Camp pipeline on a Charlotte residential subdivision. Comes out at 65.5% trap efficiency — below NCDEQ's 80%, so the example walks through forebay/PAM/upsizing remediation.
- RUSLE soil loss with cover-factor comparison on a 1-acre Asheville construction siteSame 1-acre Asheville site solved four times: bare grading, straw mulch, erosion blanket, temporary seed. Shows where the C-factor row in the RUSLE table actually moves the needle.
- Trap-efficiency check for an existing sediment basin: Camp's equation, back-solvedInherited a basin design from a similar prior project. Run the math before submitting: A_s and Q give the capture particle, then 7-bin Stokes/Camp gives 67% trap efficiency — below NCDEQ. What to do.
- Does a forebay improve trap efficiency? A worked counter-exampleA widely-repeated rule says forebays raise trap efficiency. The math says otherwise: 65.5% → 66.0% with 10% forebay, → 67.0% with 40% forebay. Forebays do other useful things — but they're not a capture-rate fix.
- PAM (polyacrylamide) in a sediment basin: from 65% to 92% trap efficiencySame 5-acre basin from scenario 1. With 5 ppm anionic PAM dosed at the inflow, the 7-bin trap efficiency moves from 65.5% to ~92% — without enlarging the basin. Dosing rate, application methods, cost, and the NPDES turbidity story.
- Detention pond routing to the pre-development peak: a 10-acre commercial site in Wake County, NCSCS runoff for pre and post conditions (14 cfs vs 41 cfs), TR-55 storage estimate, a two-stage outlet, and a full Modified Puls route that brings the 10-yr peak back under the allowable release. Every formula and number shown.
- Sizing a bioretention cell from the Water Quality Volume: a 3-acre commercial site in NCA 3-acre, 65%-impervious commercial site: runoff coefficient Rv = 0.635, Water Quality Volume = 6,900 ft³ from the 1-inch storm, and a bioretention cell sized by the Darcy filter-bed equation to ~1,540 ft² of surface with a 48-hour drawdown. Every formula shown.