RUSLE soil loss with cover-factor comparison on a 1-acre Asheville construction site
A 1-acre commercial site graded into a hillside outside Asheville. 12% average slope. The Erosion and Sedimentation Control Plan needs to defend a cover-practice choice. RUSLE solved four times for the same physical site with different C-factors. The numbers make the decision obvious.
Site inputs
| Parameter | Value | Source |
|---|---|---|
| Disturbed area | 1.0 ac | Project boundary |
| Average slope | 12% | LiDAR |
| Slope length, λ | 150 ft | Field |
| Soil texture | clay loam | SSURGO Web Soil Survey |
| R factor (Asheville) | 140 | USDA isoerodent map |
| K factor (clay loam) | 0.37 | USDA-NRCS K table |
| P factor | 1.00 | No support practice |
Step 1 — LS factor for a 12% slope
Above 9% slope, RUSLE uses a different S formulation. With m = 0.5 for slopes ≥ 5%:
Compare: a 4% slope with the same length gives LS ≈ 0.69. Tripling the slope from 4% to 12% multiplied LS by 3.1×. Slope is the single biggest physical driver after rainfall.
Step 2 — RUSLE solved four times for the same site
R, K, LS, P are fixed by the site. C is the engineer's lever. Same 1-acre site, four cover practices:
| Cover practice | C factor | A = R·K·LS·C·P (tons/ac/yr) | 1-ac total (tons/yr) |
|---|---|---|---|
| Bare soil / active grading | 0.90 | 140 × 0.37 × 2.160 × 0.90 × 1.0 = 100.7 | 100.7 |
| Temporary seeding | 0.45 | 140 × 0.37 × 2.160 × 0.45 × 1.0 = 50.4 | 50.4 |
| Erosion blanket | 0.10 | 140 × 0.37 × 2.160 × 0.10 × 1.0 = 11.2 | 11.2 |
| Straw mulch (2 ton/ac) | 0.06 | 140 × 0.37 × 2.160 × 0.06 × 1.0 = 6.7 | 6.7 |
| Permanent grass (post-stabilization) | 0.01 | 140 × 0.37 × 2.160 × 0.01 × 1.0 = 1.12 | 1.12 |
Step 3 — Volume converted to design basin storage
The active-grading scenario produces 100.7 tons/yr. NCDEQ permitting typically assumes ~9 months of active disturbance before stabilization:
At a sediment bulk density of 100 lb/ft³:
NCDEQ regulatory minimum (1,800 ft³/ac for skimmer basins) gives:
The two are close on a 1-acre site. Use 1,800 ft³. If you switch to mulch (6.7 tons/yr), the RUSLE-derived volume falls to ~100 ft³ and the regulatory minimum becomes the controlling number — but the basin still costs the same, so cover practice doesn't reduce basin construction cost on small sites. It reduces effluent sediment load, which is what matters under NPDES.
What changes if you tweak the inputs
| If you change… | The result moves… |
|---|---|
| Asheville → Charlotte (R 140 → 180) | Yield scales by 1.29×; bare-grading site → 130 tons/ac/yr |
| Slope 12% → 6% | LS drops from 2.16 to ~1.05; yield halves |
| Clay loam → sandy loam (K 0.37 → 0.27) | Yield drops 27% |
| Add diversion ditches (P 1.00 → 0.60) | Yield drops 40% on top of any cover practice |
| Slope length doubles (150 → 300 ft) | L = (300/72.6)^0.5 = 2.03; LS rises 41% |
Run the same scenario in HydroComplete
Toggle cover practices, change R/K/LS, watch the basin storage and trap efficiency update live. Built on the same RUSLE engine values used in this worked example.
Sources and further reading
- USDA-NRCS. RUSLE: Predicting Soil Erosion by Water (Agriculture Handbook 703). Renard et al., 1997.
- USDA-NRCS, NC. Isoerodent map: R = 140 for Asheville/Buncombe County.
- NCDEQ. NC Erosion and Sediment Control Planning and Design Manual. Cover practices §5.51.
- AASHTO Standard Practice. RUSLE 2 implementation for highway/construction projects.
— Michael Flynn, PE
R, K, C and LS values pulled directly from HydroComplete's SEDCAD4 RUSLE tables. Verify against your local SCS office for site-specific corrections.
Related worked examples
- Sediment basin sizing for a 5-acre residential subdivision in Mecklenburg County, NCFull RUSLE → Camp's → 7-bin Stokes/Camp pipeline on a Charlotte residential subdivision. Comes out at 65.5% trap efficiency — below NCDEQ's 80%, so the example walks through forebay/PAM/upsizing remediation.
- Trap-efficiency check for an existing sediment basin: Camp's equation, back-solvedInherited a basin design from a similar prior project. Run the math before submitting: A_s and Q give the capture particle, then 7-bin Stokes/Camp gives 67% trap efficiency — below NCDEQ. What to do.
- Does a forebay improve trap efficiency? A worked counter-exampleA widely-repeated rule says forebays raise trap efficiency. The math says otherwise: 65.5% → 66.0% with 10% forebay, → 67.0% with 40% forebay. Forebays do other useful things — but they're not a capture-rate fix.
- PAM (polyacrylamide) in a sediment basin: from 65% to 92% trap efficiencySame 5-acre basin from scenario 1. With 5 ppm anionic PAM dosed at the inflow, the 7-bin trap efficiency moves from 65.5% to ~92% — without enlarging the basin. Dosing rate, application methods, cost, and the NPDES turbidity story.
- Detention pond routing to the pre-development peak: a 10-acre commercial site in Wake County, NCSCS runoff for pre and post conditions (14 cfs vs 41 cfs), TR-55 storage estimate, a two-stage outlet, and a full Modified Puls route that brings the 10-yr peak back under the allowable release. Every formula and number shown.
- Sizing a trapezoidal roadside channel: Manning's normal depth, critical depth, and Froude numberA grass-lined trapezoidal roadside ditch carrying 25 cfs: Manning's normal depth solved by iteration (1.17 ft), velocity 3.9 ft/s, critical depth 1.05 ft, Froude 0.81 (subcritical). Then the permissible-velocity lining check and freeboard. Pure hand math, no nomographs.
- Sizing a bioretention cell from the Water Quality Volume: a 3-acre commercial site in NCA 3-acre, 65%-impervious commercial site: runoff coefficient Rv = 0.635, Water Quality Volume = 6,900 ft³ from the 1-inch storm, and a bioretention cell sized by the Darcy filter-bed equation to ~1,540 ft² of surface with a 48-hour drawdown. Every formula shown.
- Time of concentration the right way: sheet, shallow-concentrated, and channel flow (NC)A development catchment's flow path split into sheet flow (0.225 hr), shallow concentrated flow (0.197 hr), and channel flow (0.139 hr), summed to Tc = 0.56 hr (34 min). The single input that most distorts peak flow when engineers get it wrong.
- Rational method peak flow for a storm-drain inlet: composite C, IDF intensity, and the 200-acre limit (NC)An 8-acre mixed catchment to a storm-drain inlet: area-weighted C = 0.55, design intensity 5.8 in/hr at the 15-min Tc (10-yr IDF), Q = CiA = 25.5 cfs. Plus the assumptions that make the Rational method valid — and when it isn't.